In 1995 and 1996, I built a Bastidon in Provence (South of France). The project had 21 tasks (2 tasks canceled), it was planned for a duration of 33 man-day, realized in 47 man-day, used 5 m³ of concrete, 2000 kg of ciment, 300 rubble stone, 8 m³ of sand and gravel and about 100 kg of iron. All the details are defined in the document <a href="/cas/sc_bastidon.pdf">Bastidon Lou Mistraou</a>.